Wednesday, December 11, 2013

Project Management Question of the Week

During the executing phase of a project for the closing of a nuclear plant, the project manager submits to the stakeholders, including the sponsor, a progress report informing about the project performance.  Which report would that be?
  • Milestone diagram
  • GANTT chart
  • Network diagram
  • Earned Value report

No comments: