You are developing the project schedule, so you have to clarify to the rest of the team some basic concepts of network diagrams.  Which of the following  statements is correct?
  • The network diagram will change whenever the starting date changes.
  • There is only one critical path in projects.
  • The project cannot have a negative slack.
  • The critical path can include dummy activities.