Sunday, July 7, 2013

Project Management Question of the Week

The PM for Project XYZ is communicating with the stakeholders, internal and external, about the project's performance.  The report shows the actual status in relation to the following constraints: scope, time and costs.  What type of report is this?
  • Status
  • Time series
  • Earned value
  • Progress

No comments: